Guarda
Âmbito da Intervenção
The modernization on the stretch of the Beira Alta line between Guarda and Cerdeira, includes the following work:
Complete renewal of 14 km of track by replacing the bi-block concrete sleepers with multi-purpose concrete monoblock sleepers and 54 kg/m track with 60 kg/m track;
Stabilization of the track platform and improvement of the drainage system;
Stabilization of slopes;
Adaptation of the overhead contact line infrastructure;
Implementation of the Traction Return Current + Soil and Protection (RCT+TP) system;
Adaptation of the current signaling and telecommunications infrastructure.
Benefícios
The modernization of this stretch will allow speeds to be standardized through the improvement of track parameters. A new life cycle for the infrastructure will also start, now prepared for the future migration to European gauge.